Read the texts and answer the questions. Questions 1-5 refer to the following memo, form, email.

Why is the server room being relocated?

  • The current room has a mold problem
  • The building is being sold
  • Additional storage servers require more space
  • The current room failed a safety inspection

What does the inventory checklist recommend for the flagged backup power unit?

  • Moving it first, before other equipment
  • Testing it again after the move
  • Keeping it in suite 150 permanently
  • Replacing it rather than moving it

By when did CoolTech Systems confirm the cooling system installation would be complete?

  • August 22
  • August 24
  • August 25
  • August 5

According to the memo and the email, will the new cooling system be ready in time to run for 24 hours before equipment is moved on August 24?

  • No, because the installation will not be finished until August 24
  • Yes, because the installation will be finished by August 22, two days early
  • No, because CoolTech Systems did not confirm a completion date
  • Yes, but only if facilities staff replace the backup power unit first

What can be inferred about the equipment inventory checklist's role in this project?

  • It replaces the need for a cooling system
  • It is only required if equipment is damaged
  • It must be completed before the physical move begins
  • It is optional for facilities staff